Change Request - Schedule of Values - Bulk Actions - Commitment

Suggested Prior Reading

Change Request - Schedule of Values - Bulk Actions

Bulk Actions - Contract

The Bulk Actions Button has functions to automatically add the selected Line Items on a Change Request Schedule of Values to Commitments and/or Commitment Change Orders:

  • Purchase Order
  • Purchase Order Change Order
  • Subcontract
  • Subcontract Change Order

This can be an existing one or a new one (that can be created with this function).

There are several items that impact this function:

  • At least one Line Item must be Selected
  • Change Request can be in any Status
  • Can only be assigned to
    • Purchase Orders with certain Status
    • Subcontracts with certain Status
    • Purchase Order Change Orders or Subcontract Change Orders with certain Status
  • Can not already be assigned to a Commitment or Commitment Change Order

More information on each is described below:

At least one Line Item must be Selected

At least one Line Item must be selected for the Bulk Actions button to be enabled (i.e. the text is black):

If a Line Item is not selected, the Bulk Actions button is not enabled to be clicked (i.e. the text is gray):

See Change Request - Schedule of Values - Bulk Actions - Select Line Items for more information on selecting Line Items.

Change Request can be in any Status

The Change Request can be in any Status and still have its Line Items created on a Commitments and/or Commitment Change Order Schedule of Values.

Can only be assigned to Purchase Order with certain Status

The Change Request Schedule of Values Line Items can only be assigned Purchase Orders with certain Status.

They can be assigned to Purchase Orders with Status of:

  • Draft
  • Processing
  • Out for Signature
  • Submitted
  • Partially Received
  • Received

Purchase Orders with the above status will be listed to be selected to add Change Request Schedule of Values Line Items to.

They can not be assigned to Purchase Orders with Status of:

  • Approved
  • Closed

Purchase Orders with the above status will not be listed to be selected.

Can only be assigned to Subcontracts with certain Status

The Change Request Schedule of Values Line Items can only be assigned Subcontracts with certain Status.

They can be assigned to Subcontracts with Status of:

  • Draft
  • Out for Bid
  • Out for Signature
  • Submitted

Subcontracts with the above status will be listed to be selected to add Change Request Schedule of Values Line Items to.

They can not be assigned to Subcontracts with Status of:

  • Approved
  • Complete
  • Terminated
  • Void

Subcontracts with the above status will not be listed to be selected.

Can only be assigned to Purchase Order Change Orders or Subcontract Change Orders with certain Status

The Change Request Schedule of Values Line Items can only be assigned Commitment Change Orders with certain Status.

They can be assigned to Commitment Change Orders with Status of:

  • Draft
  • No Charge
  • In Review
  • Not Pricing
  • Pricing
  • Not Proceeding
  • Proceeding
  • Revised

Commitment Change Orders with the above status will be listed to be selected to add Change Request Schedule of Values Line Items to.

They can not be assigned to Commitment Change Orders with Status of:

  • Approved
  • Rejected
  • Void

Contract Change Orders with the above status will not be listed to be selected.

Can not already be assigned to a Commitment or Commitment Change Order

If this Line Item was already added to a Commitment or Commitment Change Order, it can not be added to another one.

Next Steps

Select Line Items to assign to a Contract, see Change Request - Schedule of Values - Bulk Actions - Select Line Items.

To create a new Purchase Order and add the selected Line Items to that, see Change Request - Schedule of Values - Bulk Actions - New Purchase Order.

To create a new Subcontract and add the selected Line Items to that, see Change Request - Schedule of Values - Bulk Actions - New Subcontract.

To add the selected Line Items to an existing Purchase Order or existing Subcontract, see Change Request - Schedule of Values - Bulk Actions - Add to Existing Commitment.

To create a new Purchase Order Change Order or Subcontract Change Order and add the selected Line Items to that, see Change Request - Schedule of Values - Bulk Actions - Commitments - New Change Order.

To add the selected Line Items to an existing Purchase Order Change Order or Subcontract Change Order, see Change Request - Schedule of Values - Bulk Actions - Commitments - Add to Existing Change Order.