Subcontract - Fields - Definitions
Suggested Prior Reading
Subcontracts - Core Fields Definitions
The following are definitions for the Subcontract Core Fields.
These are general definitions, along with how they may impact functionality in the system.
Each organization may have different definitions applied as required.
Some fields can also apply to Purchase Orders. This will be indicated.
It outlines general information and financial totals information.
General Information
Data | Definition |
Created | The date the Subcontract was created. This is automatically set by the system. |
Created By | The User who created the Subcontract. This is automatically set by the system based on who is logged in and creates the Subcontract. |
Status | The Status of the Subcontract. This is set by the User. The Status is chosen from a set of predefined Statuses in the system. The Status can impact the functionality available for the Subcontract. See Subcontract - Status for more information. |
Contracted Company | The Subcontractor (Company and Contact) the agreement is issued to and who is responsible for performing the work, supplying the materials or equipment or performing the service. |
Invoice Contact | The person at the Subcontractor who prepares and submits invoices for the Subcontract and handles billing questions. |
Title | A short name that identifies what the Subcontract is for, so it can be recognized at a glance in the Subcontract PDF, lists, reports, and correspondence without opening it. |
Subcontract Number | The unique identifier for the Subcontract. The User can enter the Subcontract Number or the system can automatically generate it. Note* The system will allow duplicates of the Subcontract Number as it can be entered by the user - it can also be the same as a Purchase Order Number, however it is recommended to keep them unique. |
Default Work Retainage (%) | The default percentage withheld from the value of labor or work-in-place billed on each invoice for this Subcontract. The withheld amount is held back until the terms of the order are met, typically completion or acceptance of the work. This is a default only and can be changed on each Subcontract Invoice Line Item. |
Default Material Retainage | The percentage withheld from the value of materials billed on each invoice for this Subcontract. The withheld amount is held back until the terms of the order are met, typically delivery, acceptance, or completion. This is a default only and can be changed on each Subcontract Invoice Line Item. |
Terms (drop down list of preset terms) | The agreed timeframe within which the General Contractor pays the vendor's invoices, for example, Net 30, meaning payment is due 30 days from the invoice date. Terms are preset by Users with permissions to change Settings for Commitments (See Permissions - System Features - Settings for more information). Note* There is also Payment Terms which can be used to further describe conditions or timings that must be met before payment is released. |
Description/Notes | Free-text detail about what is being purchased or done under the Subcontract, such as scope, materials, quantities, or special instructions, that doesn't fit in the Title or the other structured fields. |
Internal Notes | Free-text comments about the Subcontract that are for the General Contractor's own team only. They are not printed on the Subcontract or shared with the vendor. |
Payment Terms (text) | Free-text detail to describe the conditions or timing that must be met before payment is released on this Subcontract. |
Type | Defines whether this Commitment is a Purchase Order or Subcontract. |
Project | The Project Name that this Subcontract is being created for. |
Contract Dates
Data | Definition |
Start Date | The date the subcontractor is to begin work. |
Est. Complete Date | The planned date the subcontractor's work is to be finished. |
Actual Complete Date | The date the subcontractor actually finished the work. Compared with the estimate, it shows schedule performance. |
Contract Date | The effective date of the subcontract agreement, which may differ from the date it was signed. |
Signed Contract Received Date | The date the General Contract/Project Manager received the signed subcontract and filed it as the contract of record. |
Letter of Intent Date | The date the General Contract/Project Manager issued a letter of intent. It lets the subcontractor mobilize or start work before the formal subcontract is signed. |
Approval Letter Date | The date of the letter notifying the subcontractor that its bid or proposal is approved and the subcontract will be awarded. |
Issued On Date | The date the General Contractor/Project Manager sent the subcontract agreement to the subcontractor for review and signature. |
Execution Date | The date the subcontract was signed by all parties and became legally binding. |
Returned Date | The date the subcontractor sent the signed subcontract back to the General Contractor/Project Manager. |
Inclusions and Exclusions
Data | Definition |
Inclusions | The work, materials, equipment, and services that the subcontractor’s price covers, written out so both parties agree on what is part of the scope. |
Exclusions | The work, materials, equipment, and services that the subcontractor’s price does not cover. They are not part of the agreement unless added later by a change order. |
Other
Data | |
Attachments | Supporting files uploaded to the order, such as quotes, drawings, specifications, or correspondence. |
Attachments Uploaded (yes/no) | Indicates if at least one supporting file has been attached. |
Certificate of Insurance | Proof from the vendor's or subcontractor's insurer that the required coverage is in place. |
Certificate of Insurance Uploaded (yes/no) | Shows whether a certificate of insurance is on file. |
Certificate of Insurance - Required for Payment (yes/no) | Shows whether payment is held until a valid certificate is on file. |
Certificate of Insurance - Required for Payment - Status | The current state of the Certificate of Insurance that is required for payment: Not Reviewed, Rejected or Approved. |
Certificate of Insurance - Required for Submission (yes/no) | Indicates whether the certificate must be on file before the Vendor or Supplier can submit an invoice. |
W9 | The tax form giving the Subcontractor's legal name, tax ID, and tax classification, needed to pay and report payments to them. |
W9 Uploaded (yes/no) | Shows whether a W9 is on file. |
W9 Required for Payment (yes/no) | Shows whether payment is held until a W9 is on file. |
W9 Required for Payment Status | The current state of the W9 that is required for payment: Not Reviewed, Rejected or Approved. |
W9 Required for Submission (yes/no) | Shows whether a W9 must be on file before an invoice can be submitted. |
Lien Waivers | A signed statement from the vendor or subcontractor confirming they have been paid to a stated amount or date and giving up lien rights for that amount or period. |
Lien Waivers Uploaded (yes/no) | Shows whether a lien waiver is on file. |
Lien Waivers Required for Payment (yes/no) | Shows whether payment is held until the lien waiver is on file. |
Lien Waivers Required for Payment Status | The current state of the Lien Waiver that is required for payment: Not Reviewed, Rejected or Approved. |
Lien Waivers Required for Submission (yes/no) | Shows whether a lien waiver must accompany an invoice when it is submitted. |
Signed Documents | Documents the vendor or subcontractor has signed and returned, such as the signed order, acknowledgments, or forms. |
Signed Documents Uploaded (yes/no) | Shows whether the signed documents have been uploaded. |
Signed Documents Required for Submission (yes/no) | Shows whether signed documents must be on file before an invoice can be submitted. |
Affidavits | Sworn written statements from the vendor or subcontractor, such as confirmation that suppliers and workers have been paid. |
Affidavits Uploaded (yes/no) | Shows whether an affidavit is on file. |
Affidavits Required for Submission (yes/no) | Shows whether an affidavit must accompany an invoice when it is submitted. |
Executed Documents | The final copies of the order or agreement, signed by all parties, which become the record of the contract. |
Executed Documents Uploaded (yes/no) | Shows whether the fully signed copy has been uploaded. |
Financial Data
Data | Definition |
Amount | The total of the Amounts on all line items on the original Subcontract (before any Commitment Change Orders) (either the Amount or the Quantity x Unit Price) It excludes Taxes. It excludes Markups - except if a markup is set as a separate line items on the Schedule of Values. In that case the value of the Markup is included in the Amount. |
Markup | he Markup amount - it includes the Markups amounts from Markups that are set as:
It does not include markup values if they are set as separate line items on the Schedule of Values. In that case the value of the Markup is included in the Amount (see Amount above). |
Tax | The total value of all tax for all Line Items. |
Original Contract / Grand Total | The total value of the Subcontract including the Amounts of all Line Items, all Markups and all Taxes. |
Current Retainage | The total Retainage amount less any Retainage already released for all Approved or Completed Invoices. |
Approved Changes | The total value of all Approved Change Orders for the Subcontract including the Amounts of all Line Items, all Markups and all Taxes. |
Contract Total | The Original Contract value (the total value of the Subcontract including the Amounts of all Line Items, all Markups and all Taxes plus the Approved Changes (including the Amounts of all Line Items, all Markups and all Taxes). Note* Change Orders can be a negative amount so they would reduce the Original Contract value. |
Billed to Date | The total Work Completed for all Approved and Complete Invoices. Note* Doesn't include the tax value for the Work Completed |
Amount Remaining | The Original Contract value (the total value of the Subcontract including the Amounts of all Line Items, all Markups and all Taxes) minus the total Work Completed plus Work Completed Tax value for all Approved and Complete Invoices). |
Next Steps
New Subcontract - General Component (Overview)
OR