Change Request - Schedule of Values – Maintain - Layout and Navigation
Suggested Prior Reading
Change Request - Schedule of Values - Overview
Change Request - Schedule of Values - Maintain
Schedule of Values - Maintain - Layout and Navigation
The Schedule of Values is a component of a Change Request.
Maintaining a Schedule of Values is assuming that at least one Line Item has been previously entered for the Schedule of Values and the Change Request was saved. (If no Lines are entered on the Schedule of Values, see Change Request - Schedule of Values – Create - Layout and Navigation).
The Schedule of Values can be maintained during the edit of an existing Change Request. It is accessed through the Form Navigation Menu Options during the edit by clicking on the Schedule of Values text on the menu item. See Change Request - Schedule of Values - Maintain.
The Schedule of Values component is displayed in the middle section of the form Change Request View/Edit form.
The top and bottom sections of the Change Request View/Edit form don't change regardless of what component is displayed.
- The Form Navigation Menu Options are used to navigate to the other components (and they display on all Components)
- The Change Request Function Buttons apply to the entire Change Request including the General, Schedule of Values and Financial Markups.
For more information on the Change Request View/Edit form layout regardless of which Component is selected, see Change Request – View/Edit - Form Layout and Navigation.
The following is an example of a the Change Request View/Edit form with the Schedule of Values Component and Line Items entered and saved.

Schedule of Values Component
The Schedule of Values component consists of:
- Messages Line (highlighted in blue which may or may not display depending on the Status and other factors)
- Schedule of Values Function Buttons (functions specific to the Schedule of Values only)
- Accounting Method
- The list of the Line Items in the Schedule of Values
- Totals section

The status of the Change Request and whether or not the Line Items have been saved and whether or not the Line Item has been assigned to Commitment or Commitment Change Orders, will determine the type of functionality available (more details below).
However, none of the changes are actually saved for the Schedule of Value Line Items, until the entire Change Request is saved. This is done via the Change Request Function Buttons that appear at the bottom of the form.
While Line Items are being added, edited or deleted and before the entire item is saved, this is considered a working session. The Save or Save & Email Item Function Buttons must be used to save the entire Change Request and includes saving the Schedule of Values. The Save or Save & Email Item Function Buttons apply to the entire item, not just the Schedule of Values Component; they can be invoked from any component and will save all information on all Components.
Schedule of Values Component - that can be edited
If this Change Request is in a Status that can be edited, (see Change Request - Status), there are Schedule of Values Function Buttons to:
- Add individual Line Items
- Import Line Items from a File
- Perform Bulk Actions:
- Add the Line Item to an existing or new Contract Change Order
- Add the Line Item to an existing or new Commitment or Commitment Change Order
- Send RFQs
- Edit existing Line Items inline within the Schedule of Values (for the information that can be edited)
- Delete a Line Item
Once Line Items are entered, the Accounting Method is displayed but it is grayed out and can not be changed.
The Cost Code and Cost Type for a Line Item (and Sub Jobs if turned on) can be edited, but only until the form is saved. In the example below, the form has not been saved so the Cost Code and Cost Type (and the Sub Job if applicable) are still drop down fields that can be clicked and changed.

Once the form is saved, the Cost Code and Cost Type (and Sub Job if applicable) can not be changed. They are a display only and not a drop down. See the example below.

For more information on Sub Jobs, see Sub Jobs - Overview (Note* Sub Jobs are not shown in these examples).
Approved Change Request - Schedule of Values Component
Schedule of Values can only be maintained for Change Requests in certain statuses. If the Schedule of Values is Approved, it can't be changed. Note* The Status can be changed while editing the Schedule of Values and if it is changed to Approved the current display is updated to reflect the functionality available with the new Status.
A message displays at the top of the Schedule of Values component indicating this.
Some function buttons don't display nor does the Accounting Method display and none of the Line Items can changed or deleted or new line items added directly from this form.
Note* However, Line Items can still be created on Contract Change Orders, Commitments or Commitment Change Orders and/or RFQs can be sent through the Bulk Actions function. See Change Request - Add/Edit - Bulk Actions.

Void or Rejected Change Request - Schedule of Values Component
Schedule of Values can only be maintained for items in certain statuses. If the Schedule of Values is Void or Rejected, it can't be changed.
A message displays at the top of the Schedule of Values component indicating this.
No function buttons display nor does the Accounting Method and none of the Line Items can changed or deleted or new line items added directly from this form.

Totals Section
Each Schedule of Values has a Totals section:
- Subtotal
- Taxes (if applicable)
- Grand Total
The Subtotal is the Subtotal of all the Line Items (which is the Revenue plus the Financial Markups if applicable).
The Taxes are the total of all Taxes for all Line Item.
The Grand Total is the Subtotal plus Taxes.
This information is automatically calculated. As Line Item values are entered it automatically updates to reflect the information (but the form has to be saved to retain the changes).
Next Steps
Add a Schedule of Values Line Item, see Change Request - Schedule of Values - Add Line Item.
Bulk Import Schedule of Values Line Items, see Change Requests - Schedule of Values - Import.
Edit a Schedule of Values Line Item before the Line Item has been saved, see Change Request - Schedule of Values - Edit Line Item (before Save).
Edit a Schedule of Values Line Item after the Line Item has been saved, see Change Request - Schedule of Values - Edit Line Item (after Save).
Delete a Schedule of Values Line Item, see Change Request - Schedule of Values - Delete Line Item.
To create the Schedule of Value Line Item(s) automatically on a Contract Change Order, Commitment or Commitment Change Order and create an association to this Line Item, see Change Request - Schedule of Values - Bulk Actions.